Student Center Renovation Update: October 12, 2012

Work on the $6 million Student Center renovation is rapidly moving forward. Flooring is being installed in the new Skeller, the elevator installation is nearly complete, and electrical wiring has begun. See photos of the progress here: http://web.randolphcollege.edu/studentcenter/slideshow/oct12/index.html. Check out comprehensive coverage of the renovation project at www.randolphcollege.edu/studentcenter.




Work has begun on the new outside deck that will wrap around the Student Center.

A view from the WWRM deejay booth on the second floor.

The new theatre on the third floor will provide a unique space for events, lectures, and other performances.