Thursday, January 12, 2012

Student Center Renovation Update: January 11, 2012










When Randolph community members left campus in December for the winter break, construction crews were still installing steel beams in the Student Center facility, and floor work was only in the beginning stages. The work completed during the past few weeks has significantly changed views in the interior of the facility. Steel framing is in place along with new flooring, and crews have now moved to the upper floors to begin the rebuilding process in those areas. On the exterior, workers continue the brick work required to install windows in what is now just a large opening into the facility. Renovations also continue in other areas of the facility, including the rear, which previously housed the Skeller.